The constraint
The house stayed occupied, and a cast-iron stack sat two studs away from the cut.
Outcome
One room now, with the beam invisible and the stack relocated before the plaster crew arrived.
Scope
- 01Temporary shore on both floors
- 02Flush LVL package and new king studs
- 03Reframed window seat that shared the same wall
- 04Sequence that let the plumber move the stack before drywall